Introduction
- The Government of India has launched the Atal Mission for Rejuvenation and Urban Transformation (AMRUT) with the aim of providing basic civic amenities like water supply, sewerage, urban transport, parks as to improve the quality of life for all especially the poor and the disadvantaged.
- Open space is very essential on day today life where kids got place to play, Middle aged or old age people got place for jogging, meditation and yoga for better and healthy life.
- Cuttack Municipal Corporation has been identified 21 no.s of parks project comes under AMRUT in municipal areas which development costing around 8.85 Cr.
- The said project approved in 3 SAAP Year(2015-16), (2016-17),(2017-18).
- Out of 21 Parks 15 no.s of parks are completed and others are in progress.
List of Parks
- Chandan Pokhri Park, Near SGBL Mall, Tala Telenga Bazar
- Akhaya Mohanty Park, Near SUN Hospital, Biju Pattanaik Chowk
- Biswanath Pandit Park, Khannagar
- Gopabandhu Park, Near Samaj Office
- Chahata Park, Near Chahata Chowk.
- Gandhi Smruti Park, Telengapentha
- Jagatpur Children Park, Near Gopabandhu Nagar,Jagatpur
- Jugal Kishore Park, CDA Sector 09
- Gouri Shankar Park, Choudhury Bazar
- Madhukunj Park, Near Deer Park, Tulsipur
- Mahanadi Jobra Park, Jobra
- Jayaprakash Narayan Park, CDA Sector 06
- Biren Mitra Park, CDA Sector 09
- Chahata Nagar Park, Chahata Chowk
- Ramadevi Park, Puri Ghat
- Sarangdhar Park, Jhola Sahi
- Sishubhawan Park, Infront of Sishu Bhawan
- Khannagar Park, Khannagar
- Sahid Park, Machuua Bazar, Infront of LIC Head Office.
- Andarpur Park, Kalyan Nagar
Sl.No | Name of the Park as per SAAP | Package/ Cluster with code | DPR Approval SLTC date | SAAP approved cost | SLTC approved cost | TS date | DTCN received Y/N | NIT Floated Y/N Date of Floating NIT | Bid Evaluation Received Y/N (Date to be mentioned) | Work Order issued Y/N If "Y" date to be mentioned | Schedule date of completion as per contract | Physical* Progress in% | Financial* *Progress in % | Remarks/ Reason of Delay if any (in bullets) |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Development of Chandan Pokhari Park in Cuttack | AMRUT/OD/ Cuttack/PR/02 | 19.01.16 | 0.84 | 0.84 | 09.02.16 | Yes | Yes(06.05.16) | Yes(19.05.17) | Yes(9.11.16) | Within Six Months | 100% Work Completed | 775919/- paid | Inagurated on 28.12.2018 |
2 | Development of Akhaya mohanty Park in Cuttack | AMRUT/OD/ Cuttack/PR/04 | 19.01.16 | 0.33 | 0.33 | 09.02.16 | Yes | Yes(06.05.16) | Yes(19.05.17) | Yes(10.08.16) | Within Six Months | 100% Work Completed | 1315803/- paid + 1200000/- paid | Inaugurated on 20.11.17 |
3 | Development of Biswanath Pandit Park in Cuttack | AMRUT/OD/ Cuttack/PR/05 | 19.01.16 | 0.42 | 0.42 | 09.02.16 | Yes | Yes(06.05.16) | Yes(19.05.17) | Yes(10.08.16) | Within Six Months | 100% Work Completed | 3398439/- paid | Inaugurated on 31.08.17 |
Sl.No | Name of the Park as per SAAP | Package/ Cluster with code | DPR Approval SLTC date | SAAP approved cost (in cr) | SLTC approved cost (in cr) | TS date | DTCN received Y/N | NIT Floated Y/N Date of Floating NIT | Bid Evaluation Received Y/N (Date to be mentioned) | Work Order issued Y/N If "Y" date to be mentioned along with cost in cr. | Schedule date of completion as per contract | Actual Physical* Progress in% | Financial* *Progress in % | Remarks/ Reason of Delay if any (in bullets) |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Development of Gopabandhu Park near Samaj Office in Cuttack | AMRUT/OD /CUTTACK/PR/03 (CLUSTER 1) | 21.11.16 | 1.2 | 1.9 | Yes | Yes(16.12.16) | Yes(07.01.17) | 17.05.17 | in 9 months | 100% work completed | Inagurated on 28.12.2018 | ||
2 | Development of Chahata Park in Cuttack | AMRUT/OD /CUTTACK/PR/03 (CLUSTER 1) | 21.11.16 | 1.2 | 1.9 | Yes | Yes(16.12.16) | Yes(07.01.17) | 17.05.17 | in 9 months | 40% work completed | Trackwork Partially completed.As per instruction park should be completed by Oct'19 | ||
3 | Development of Gandhi Smriti Udayan (Telenga Pentha) in Cuttack | AMRUT/OD /CUTTACK/PR/03 (CLUSTER 1) | 21.11.16 | 1.2 | 1.9 | Yes | Yes(16.12.16) | Yes(07.01.17) | 17.05.17 | in 9 months | 100% work Completed | To be inagurated on 02.10.2019 | ||
4 | Construction of Children Park at Jagatpur | AMRUT/OD /CUTTACK/PR/03 (CLUSTER 1) | 21.11.16 | 1.2 | 1.9 | Yes | Yes(16.12.16) | Yes(07.01.17) | 17.05.17 | in 9 months | 30% work completed | Boundary wall partially completed. As per instruction park should be completed by Oct'19 | ||
5 | Development of Jugal Kishor Park at Sector 9 CDA | AMRUT/OD/ CUTTACK/PR/09 (CLUSTER 2) | 21.11.16 | 1.05 | 1.29 | Yes | Yes(16.12.16) | Yes(07.01.17) | 17.05.17 | in 8 months | 100% work completed | Inaugurated on 21.02.18 | ||
6 | Development of Gourishankar Ray Park in Cuttack | AMRUT/OD/ CUTTACK/PR/09 (CLUSTER 2) | 21.11.16 | 1.05 | 1.29 | Yes | Yes(16.12.16) | Yes(07.01.17) | 17.05.17 | in 8 months | 100% work completed | Inaugurated on 06.07.18 | ||
7 | Development of Madhukunja Park in Cuttack | AMRUT/OD/ CUTTACK/PR/09 (CLUSTER 2) | 21.11.16 | 1.05 | 1.29 | Yes | Yes(16.12.16) | Yes(07.01.17) | 17.05.17 | in 8 months | 100% work completed | Inaugurated on 11.04.18 | ||
8 | Development of Mohanadi Park at Jobra in Cuttack | AMRUT/OD/ CUTTACK/PR/09 (CLUSTER 2) | 21.11.16 | 1.05 | 1.29 | Yes | Yes(16.12.16) | Yes(07.01.17) | 17.05.17 | in 8 months | 100% work completed | 2041616/- paid | Inaugurated on 01.09.17 |
Sl.No | Name of the Park as per SAAP | Package/ Cluster with code | DPR Approval SLTC date | SAAP approved cost (in cr) | SLTC approved cost (in cr) | TS date | DTCN received Y/N | NIT Floated Y/N Date of Floating NIT | Bid Evaluation Received Y/N (Date to be mentioned) | Work Order issued Y/N If "Y" date to be mentioned with cost in cr. | Schedule date of completion as per contract | Physical* Progress in% | Financial* * Progress in % | Remarks/ Reason of Delay if any |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Renovation of Jaya Prakash Narayan Park, Sector -6, CDA | AMRUT/OD/ CUTTACK/PR/10 (PKG-1) | 14.02.17 | 1 | 1.9 | 20.02.17 | Yes | Yes(17.05.17) | Yes(20.06.17) | 14.12.17 | Within 9 Months | 70% work completed | After restroration of boundary wall balance work will be taken up. | |
2 | Renovation of Biren Mitra Park, Sector-11, CDA | AMRUT/OD/ CUTTACK/PR/10 (PKG-1) | 14.02.17 | 1 | 1.9 | 20.02.17 | Yes | Yes(17.05.17) | Yes(20.06.17) | 14.12.17 | Within 9 Months | As per instruction execution work will be completed by Oct'19 | ||
3 | Renovation of Biju Pattnaik park | AMRUT/OD/ CUTTACK/PR/10 (PKG-1) | 14.02.17 | 1 | 1.9 | 20.02.17 | Yes | Yes(17.05.17) | Yes(20.06.17) | 14.12.17 | Within 9 Months | To be cancelled | ||
4 | Construction of New Park at Chahata Nagar, Tulasipur | AMRUT/OD/ CUTTACK/PR/11 (PKG-2) | 03.03.17 | 0.8 | 1.34 | 14.03.17 | Yes | Yes(17.05.17) | Yes(20.06.17) | 18.12.17 | Within 9 Months | As per instruction execution work will be completed by Oct'19 | ||
5 | Renovation of Rama Devi Children Park, Purighat | AMRUT/OD/ CUTTACK/PR/11 (PKG-2) | 03.03.17 | 0.8 | 1.34 | 14.03.17 | Yes | Yes(17.05.17) | Yes(20.06.17) | 18.12.17 | Within 9 Months | 100% work completed | Inagurated on 31.08.2019 | |
6 | Renovation of Sarangadhar Park, Jholasahi | AMRUT/OD/ CUTTACK/PR/11 (PKG-2) | 03.03.17 | 0.8 | 1.34 | 14.03.17 | Yes | Yes(17.05.17) | Yes(20.06.17) | 18.12.17 | Within 9 Months | 100% work completed | Inagurated on 31.08.2019 | |
7 | Renovation of Sishu Bhawan Park | AMRUT/OD/ CUTTACK/PR/11 (PKG-2) | 03.03.17 | 0.8 | 1.34 | 14.03.17 | Yes | Yes(17.05.17) | Yes(20.06.17) | 18.12.17 | Within 9 Months | 100% work completed | Inagurated on 31.08.2019 | |
8 | Renovation of Children Park, Khannagar | AMRUT/OD/ CUTTACK/PR/12 (PKG-3) | 03.03.17 | 0.66 | 0.2 | Yes | Yes(17.05.17) | Yes(20.06.17) | 22.11.17 | Within 3 Months | 100% work completed | Inaugurated on 26.05.18 | ||
9 | Renovation of Sahid Park, Nuapatna | AMRUT/OD/ CUTTACK/PR/13 (PKG-4) | 03.03.17 | 0.6 | 0.63 | Yes | Yes(17.05.17) | Yes(20.06.17) | 18.12.17 | Within 6 Months | 100% work completed | Inagurated on 25.12.2018 | ||
10 | Construction of new Park , Andarpur | AMRUT/OD/ CUTTACK/PR/13 (PKG-4) | 03.03.17 | 0.6 | 0.63 | Yes | Yes(17.05.17) | Yes(20.06.17) | 18.12.17 | Within 6 Months | 100% work completed | Inagurated on 31.08.2019 |